Scrum Master Interview Question #8

Your working with a team of the first time, they do not do task break down at the moment, scrum-masterexplain what the benefits are to the team if they start  task break down

What do you say ?

Posted in Agile Roles, Interview Questions, Scrum Master | Leave a comment

SAFE PI Planning Review Checks #2

If you have same sprint dependencies, have a risks be recorded and agreed with your RTE and PM.

Posted in Uncategorized | Leave a comment

SAFE PI Planning Review Checks #1

At any point in the PI  does your teams plan exceed your agreed stretch goal.

Posted in Uncategorized | Leave a comment

Scrum Master Interview Question #7

Your team has just finished a very hard sprint, they came up short and failed the sprint. scrum-masterThey did not deliver some key stories, the PO is angry and the team are angry with the PO, the retro is turning into open warfare.

What do you say to the group?

Posted in Agile Roles, Interview Questions, Scrum Master | Tagged , , , , | 1 Comment

75% lower incident costs Locate your Scrum Master with your team

So for the scrum master to be a success , they need to not only run the standard ritual and walk through the processes, they need to share time with the team where open unofficial conversations take place, where team members feel free to share concerns that may not be so easy to do formally.  Most scrum masters will quickly start to pickup themes and trends in issues and be ablPicture2e to either address or escalate them before they are are problem. Typically prevention, cost and delay, disruption and management overhead is at least 75% cheaper than cure.  So have your scrum master on site, get them searching and removing issues before they trigger, save that time, remove that wastes effort on fixing preventable issues.

This is a big part of a good Scrum Masters job  I call SMBWA (Scrum Mastering by Walking Around) like GEMBA in Lean or others call it  “go see for yourself”. The difference here is in lean its about looking atthe problem, going in seeing it in SMBWA its about hunting down isses and killing them before they catch fire. An issue once it catches first  severely reduces effectiveness of the team and often  damages the product and the team moral. It better have some one looking for and resolving issues before they get expensive, that’s the role of the scrum master.

This is why the Scrum Master needs to be with the team, to walk the floor as they do there normal role, listing to background conversations, talking to people in coffee areas, taking the temperature. Many problem that can delay or derail project and programs exist in those grey areas for days or even weeks before they ignite and raise to the leadership level.  Yes if they are doing their job well you will save very significant amounts of time and money as the prevent incidents from ever happening and make sure they get resolved quickly.

Posted in Agile, Agile Coach, CBWA, GEMBA, ScrumMaster | Tagged , , , , | Leave a comment

Agile Coach Interview Question #3

Your working with ajigsaw new Scrum Master,  he is having troubling getting the team to do task breakdown and  wants to know what we would lose if the team did not do it.

Whats your answer ?

Posted in Agile Coach, Agile Roles, Interview Questions | Tagged , , , , | Leave a comment

Scrum Master Interview Question #6

You have a new PO, she is has just finished her training, so far she has done very well. You have been impressed by her  first sprint planscrum-masterning. Your just about to start the last session of the day, just before it starts she pulls you aside  says “what should I be focusing on here”.

What do you answer ?

Posted in Agile Roles, Interview Questions, Scrum Master | Tagged , , , , | Leave a comment